Romania to allocate grid capacity through auctions
Countries in Europe and beyond are racing to attract such investments with incentives, while neglecting digitalization, power lines and transformers. Romania decided to
Romania shifting to an auction-based power grid
Under the new rules, the transmission system operator ("TSO") will operate a dedicated auctioning platform for allocating available grid capacities in the 110kV and medium voltage networks of the distribution
Romania Tenders | RFP, Bids, eProcurement | Romania
This is a comprehensive database of all tenders and contracts issued by government departments, local authorities and other public entities in Romania. The database is updated
Intended changes to the grid connection rules in Romania – the
On 1 February , the National Energy Regulatory Authority (ANRE) in Romania published for consultation an order aimed at approving new rules in the power grid connection sector.
Romania shifts towards auction-based mechanism
Starting 1 July: bidding sessions will be held daily for allocating available capacity. The bidders will be able to place bids for capacity for one year (of the tendered ten-year period).
Romania power Tenders, Bids and RFP
Latest Romania power Tenders, Government Bids, RFP and other public procurement notices related to power from Romania. Users can register and get updated
We are launching an auction of over 132 million lei for equipment
This equipment will replace the old installations, contributing to the modernization of the network, improving the performance of the distribution network and reducing the number of
Romania Energy, Power and Electrical bids and eProcurement
View Energy, Power and Electrical government contracts and RFPs from Romania. Bid on readily available Energy, Power and Electrical tenders from Romania with the best and
Romania announces new auction-based mechanism for grid
The Romanian Energy Regulatory Authority (ANRE) has approved a new methodology for the allocation of electricity grid capacity of new production sites equal or
Romania Electricity Distribution Tenders
Explore the latest Romania Electricity Distribution Tenders and gain access to real-time government bids, eProcurement updates, and detailed information on government contracts in
Romania to allocate grid capacity through auctions
Countries in Europe and beyond are racing to attract such investments with incentives, while neglecting digitalization, power lines and transformers. Romania decided to
Romania shifting to an auction-based power grid access mechanism
Under the new rules, the transmission system operator ("TSO") will operate a dedicated auctioning platform for allocating available grid capacities in the 110kV and medium
Romania shifts towards auction-based mechanism for grid access
Starting 1 July: bidding sessions will be held daily for allocating available capacity. The bidders will be able to place bids for capacity for one year (of the tendered ten-year period).